New Recycling & Waste Transfer Station
View allKing County is in the process of designing a new recycling and garbage transfer station to be built in Algona that will replace the 1960s-era Algona Transfer Station. The new station will offer a full array of recycling services, hazardous waste disposal for households and qualifying business, sustainable building features, offsite wetlands improvements, on-site creek enhancements, public art, and other community benefits. King County will keep the existing Algona Transfer Station open throughout construction of the new facility.
| Date | Actions/events |
|---|---|
| Spring - Fall 2021 | Final design |
| Spring 2022 - Summer 2024 | Construction of new facility |
| Mid 2024 | New facility opens to the public |
This project is primarily being financed through the issuance of LTGO bonds.